1/. Commissioning Section 2 (1 Mai station – Bazilescu station) of Metro Line 4 in Bucharest, in July, 2011, with the following:
Length: 2.2 km
No. stations: 2
Tunnels:
- shield method: twin tunnels, 6.4 m in diameter, total length: 3405 m
- cut and cover: 504 m (including stations).
![Jiului station Jiului station](/images/visuels/corporate/nations/romania/1_underground2011_1.jpg)
![Bazilescu station Bazilescu station](/images/visuels/corporate/nations/romania/1_underground2011_2.jpg)
2/. Under construction: Metro Line 5
Lot 1.2 - Valea Ialomitei Sector (cut and cover tunnel, station and depot) awarded to Max Bögl.
Lot 1.1 – Raul Doamnei – Eroilor (6 km), TBM method tunnels, 9 stations cut and cover method awarded to ASTALDI-FCC-DELTA ACM -AB CONSTRUCT JV.
![Metro Line 5 Metro Line 5](/images/visuels/corporate/nations/romania/1_underground2011_3.jpg)
3/. In tender process: Metro Line 4, Section 3, Bazilescu – Straulesti: 2 stations, 1 depot, 2.7 km in length.